Abschlagsrechnung under § 632a BGB: BGB contract and consumer construction contract
If VOB/B is not agreed, the BGB governs progress payments. For contracts with private individuals for new buildings or substantial conversions, stricter rules apply: an upper limit and security for the customer.
Last updated 13.11.2026 · 4 min read · Provisions checked against the statute and VOB text
Key points at a glance
- Without VOB/B, the progress payment follows § 632a BGB: you can demand a progress payment in the amount of the value of the work performed in conformity with the contract.
- The work must be proved by a statement that allows a quick and reliable assessment (§ 632a para. 1 sentence 5 BGB).
- If work is not in conformity with the contract, the client can refuse payment of an appropriate part of the progress payment. The burden of proof for conformity with the contract remains with the contractor until acceptance.
- For the consumer construction contract (§ 650i BGB), progress payments in total may not exceed 90 percent of the total remuneration including Nachträge (§ 650m para. 1 BGB).
- There, security of 5 percent must be provided with the first progress payment (§ 650m para. 2 BGB).
When does the BGB apply instead of VOB/B?
VOB/B applies only if it has been agreed. In contracts with private individuals, smaller orders and craftsman services, this agreement is often missing. Then the BGB provisions on contracts for work and construction contracts apply. The progress payment is in § 632a BGB. The VOB/B rules on progress payments (§ 16 para. 1 VOB/B) then do not apply. What they look like is explained in the article Abschlagsrechnung under VOB/B.
What § 632a BGB requires
Claim. The contractor can demand a progress payment in the amount of the value of the work performed by him and owed under the contract. A rigid grid of instalments is not needed for this. What matters is what has actually been performed.
Defects. If the work performed is not in conformity with the contract, the client can refuse payment of an appropriate part of the progress payment. The burden of proof for work in conformity with the contract remains with the contractor until acceptance.
Proof. The work must be proved by a statement that must allow a quick and reliable assessment. In practice this means quantities per item with reference to the Angebot or bill of quantities (Leistungsverzeichnis), for areas with Aufmaß and plan.
Materials and components. The claim also applies to delivered or specially made materials and components, if ownership is transferred to the client at its choice or corresponding security is provided. The security can also be a guarantee or a payment promise from a credit institution or credit insurer (§ 632a para. 2 BGB).
Consumer construction contract: additional rules
A consumer construction contract exists when a contractor is obliged by a consumer to build a new building or to carry out substantial conversion work on an existing building (§ 650i para. 1 BGB). Then § 650m BGB also applies:
| Rule | Reference |
|---|---|
| With the first progress payment, 5 % security for timely completion without material defects | § 650m para. 2 sentence 1 BGB |
| If the remuneration increases by more than 10 %, a further 5 % of the additional claim with the next progress payment | § 650m para. 2 sentence 2 BGB |
| At the contractor's request, the security can be provided by retention | § 650m para. 2 sentence 3 BGB |
| Security also by guarantee or payment promise from a credit institution or credit insurer | § 650m para. 3 BGB |
Whether an order counts as a consumer construction contract depends on the individual case (new building or substantial conversion). A single repair or a trade without conversion character is generally not covered. If in doubt, have the classification checked legally.
How to proceed
- Clarify the legal basis: VOB/B agreed or not? Consumer as client? New building or substantial conversion?
- Measure the state of work: record quantities per item, charge work only as far as it has been performed and is in conformity with the contract.
- Attach the statement: items, quantities, prices and reference to the contract. For areas, add Aufmaß and plan.
- Check the limit: for the consumer construction contract, calculate the sum of all progress payments against 90 % of the total remuneration.
- Mind the security: for the consumer construction contract, clarify the 5 % before or with the first progress payment.
- Check mandatory details and tax as with any invoice (§ 14 UStG).
Frequently asked questions
Can I demand progress payments at all without VOB/B?
Yes. § 632a para. 1 BGB gives the contractor the claim to a progress payment in the amount of the value of the work performed in conformity with the contract.
Do I need a payment plan in the contract for that?
The statutory claim exists without a payment plan. An agreed payment plan can however regulate the progress payments contractually; then it applies.
May the customer withhold the whole progress payment in case of defects?
They can refuse an appropriate part (§ 632a para. 1 sentence 2 BGB), not everything across the board. The amount depends on the defect.
Does the 90 percent limit also apply towards businesses?
No. § 650m BGB concerns the consumer construction contract. For contracts with business customers, § 632a BGB applies without this limit.
What about the security of 5 percent?
For the consumer construction contract, it is to be provided to the consumer with the first progress payment, at the contractor's request by retention (§ 650m para. 2 BGB).
Sources and status
- § 632a paras. 1 and 2 BGB – Abschlagszahlungen (checked against the official norm text in the BauWalker corpus)
- § 650i para. 1 BGB – Verbraucherbauvertrag
- § 650m paras. 1 to 3 BGB – Abschlagszahlungen; Absicherung des Vergütungsanspruchs
- As of: 13.11.2026. General information, not legal advice. The classification as a consumer construction contract and the validity of deviating agreements should be checked in the individual case.
How it works in BauWalker
BauWalker prepares Abschlagsrechnungen in German and calculates amounts and tax by fixed rules. Whether the contract is to be treated under the BGB or VOB/B, you check in the contract text.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
What Is an Abschlagsrechnung under VOB/B?
What an Abschlagsrechnung (interim invoice) is, when you can issue one under VOB/B and what the document must contain.
Schlussrechnung (final invoice) under VOB/B: deadline, verifiability, payment
By when the final invoice must go out, what verifiable means, when the money falls due and how the reservation on final payment works.
Security for tradespeople under § 650f BGB: how to demand it
When you, as a tradesperson, can demand security for your unpaid remuneration, how high it is, what deadline to set and what applies if the client refuses.