Screed: checking readiness for flooring, CM measurement and drying time correctly

A screed that is too damp often shows only months after the flooring: blisters, joints, mould. Anyone who measures readiness for flooring and documents the result shifts the risk to where it belongs.

Last updated 20.10.2026 · 5 min read · Technical rules reproduced in substance, the manufacturers’ information and the current data sheets are authoritative

Screed cross-section with CM measuring device and drying
Illustration, created with AI

Key points at a glance

  • Belegreife (readiness for flooring) means that the residual moisture of the screed is below the limit value for the intended floor covering. What is binding is the measurement, not the time it has been laid.
  • The usual method is the CM measurement (calcium carbide method) at representative measuring points, with a record.
  • Guide values (common practice): cement screed about 2.0 CM-%, with underfloor heating about 1.8 CM-%. Calcium sulphate screed about 0.5 CM-%, with underfloor heating about 0.3 CM-%. The floor covering and adhesive manufacturer may require stricter values.
  • The flooring installer must check the substrate and, if there are defects, notify concerns (§ 4 para. 3 VOB/B).
  • The rule of thumb “1 week per cm” is no substitute for a measurement.

What readiness for flooring means

After installation, screed contains more water than it needs to set. This water must evaporate before a covering that traps it is laid (parquet, PVC, textile coverings, tiles in thin bed depending on the system). Otherwise swelling, deformation, detachment, odour and mould are the risk.

A screed is belegreif when the measured residual moisture is below the limit value that applies to the combination of screed type, covering, adhesive and heating. The age of the screed alone says nothing.

Which types of screed are there?

TypeCodeSpecial feature
Cement screedCTdries more slowly, robust against moisture
Calcium sulphate screed (anhydrite)CAlower limit values, sensitive to moisture
Mastic asphaltASis not tested for moisture like CT or CA
Synthetic resin screedSRproperties as per manufacturer’s information

For the screed standard DIN 18560 and the flooring works (DIN 18365 in VOB/C), the exact requirements are to be looked up there.

The CM measurement

The calcium carbide method is the usual method on site:

  1. Take a sample (material from the entire screed thickness, crushed).
  2. Weigh it into the CM bottle with the calcium carbide ampoule.
  3. Shake the device: the water from the sample reacts and the pressure is measured.
  4. Read the value (CM-% relative to the sample mass) and compare it with the limit value.

Measuring points should be chosen to be representative: not just at the edge but also in the open area, in rooms with different loads and at critical places (door thresholds, water points, heating circuits). With underfloor heating, the screed is function-heated and readiness-heated before the measurement, and the measuring points are chosen so that heating pipes are not damaged. The exact number and position depend on data sheets and the client’s requirements.

Guide values (practice, for orientation)

Screedwithout underfloor heatingwith underfloor heating
Cement (CT)≤ 2.0 CM-%≤ 1.8 CM-%
Calcium sulphate (CA)≤ 0.5 CM-%≤ 0.3 CM-%

These values are guide values for common coverings. What is authoritative is the information from the screed, covering and adhesive manufacturers and the data sheets of the trade associations. For vapour-tight or particularly moisture-sensitive coverings, lower limit values often apply.

Drying time: rule of thumb and reality

A well-known rule of thumb says: about 1 week per cm of screed thickness up to 4 cm, above that about 2 weeks per cm (for cement screed under favourable conditions, about 20 °C and 65 % relative humidity). That is a planning value, not proof. Construction moisture, cold rooms, closed windows, high humidity and additional sources of water extend the drying time considerably.

Measures for drying:

  • Ventilate (in a controlled way, not just tilted windows), heat and, if necessary, use construction dryers.
  • With heated screed: heating record with heating-up and cooling-down phases.
  • Fast-setting screeds only with the manufacturer’s proof.

The measurement record

A usable record contains:

  1. Construction project, room, screed type, thickness, installation date.
  2. Measurement date, measuring device, tester.
  3. Measuring point (sketch or photo) and measured value for each point.
  4. Room climate (temperature, humidity).
  5. Limit value and its source (manufacturer’s information, data sheet).
  6. Result: ready for flooring yes or no.
  7. Signatures of the tester and, if possible, the client (Auftraggeber) or site manager.

Who is responsible?

  • Screed layer: Owes a screed free of defects. It cannot release the screed for any covering, only certify its condition.
  • Flooring installer: Must check the substrate (including moisture) and, if it has concerns, notify them in writing before starting, for example if residual moisture is too high or the heating record or documentation is missing (§ 4 para. 3 VOB/B). See Bedenkenanmeldung.
  • Client/site management: Scheduling. Anyone who forces the date before the screed is ready bears the risk if the flooring installer has properly notified concerns.

If the flooring is delayed because the screed is still too damp, this can be a hindrance if the cause lies within the responsibility of the client or the previous trade. See Behinderungsanzeige.

Typical mistakes

  • Judged by laying time only.
  • Measurement at one point and the result transferred to the whole area.
  • Heated screed covered without a heating record.
  • Wrong limit value (cement instead of anhydrite, with or without underfloor heating).
  • No documentation: in a dispute the screed is regarded as “probably too damp”.
  • Screed wetted afterwards through open windows in rain, water damage or plastering work.

Frequently asked questions

Is the rule of thumb “1 week per cm” enough?

No. It serves for planning. What is decisive is the measured residual moisture.

Who carries out the CM measurement?

Usually the flooring installer or an expert. The screed layer can also measure. What matters is that the record is comprehensible.

Does the same limit value apply to parquet and PVC?

Not necessarily. Type of covering, adhesive and manufacturer specify values. The manufacturer’s information is authoritative.

What should I do if the screed is still too damp?

Keep drying and measure again, postpone the date and document the delay. Notify concerns in writing if the date is to be kept.

Do I also have to measure for tiles?

As a rule yes, if thin-bed mortar or waterproofing is used. Check the manufacturer’s information.

Sources and status

  • § 4 para. 3 VOB/B – concerns; § 13 para. 3 VOB/B – defect claims
  • DIN 18560 (screeds in building construction), DIN 18365 (VOB/C, flooring works) and data sheets of the trade associations: not checked word for word here, limit values reproduced in substance as orientation.
  • Stand: 19.10.2026. The manufacturers’ information and the current data sheets are authoritative.
  • Quotations of statutory text are given in translation; the German wording is authoritative.

How it works in BauWalker

BauWalker files the records, photos and documents of a construction project in one property file, so that measurement records can be found later. You carry out the measurement yourself.

This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.