Bedenkenanmeldung under § 4 para. 3 VOB/B: when you are liable if you stay silent
If you realise that the design or earlier work is wrong and build anyway, you are liable for the defect in case of doubt. The notice of concerns (Bedenkenanmeldung) is your protection, but only if it is timely, in writing and specific.
Last updated 20.10.2026 · 5 min read · Provisions checked against the statute and VOB text

Key points at a glance
- Concerns about the method of execution, materials or components supplied by the client and work by other contractors must be notified without delay, if possible before work starts, and in writing (§ 4 para. 3 VOB/B).
- Without notice, you are liable for defects that go back to the specification, instructions, material or earlier work of the client (§ 13 para. 3 VOB/B).
- With notice, the client remains responsible for its information, instructions and supplies.
- You are not a designer: you must raise what you, as a specialist contractor, recognise or ought to recognise.
- The Bedenkenanmeldung is not a notice of hindrance (Behinderungsanzeige). The two letters have different functions and may both be needed.
What the Bedenkenanmeldung is for
The contractor (Auftragnehmer) owes a work free of defects. But what if the defect is not due to your work, but to a mistake in the design, in the material supplied by the building owner or in the work of the previous trade? Two rules work together here:
- § 13 para. 3 VOB/B: If a defect is due to the specification, to instructions of the client (Auftraggeber), to materials or components supplied or prescribed by the client, or to the condition of earlier work by another contractor, the contractor is liable nonetheless, unless it has given the notice incumbent on it under § 4 para. 3.
- § 4 para. 3 VOB/B: Anyone who has concerns must notify them without delay, if possible before work starts, in writing. The client remains responsible for its information, instructions and supplies.
With the notice, you therefore shift the risk back to the party who caused it.
What concerns can relate to
§ 4 para. 3 VOB/B names three areas:
| Area | Examples |
|---|---|
| Intended method of execution (including protection against accident hazards) | Design contradicts the recognised rules of technology, unsuitable build-up, missing protection |
| Quality of the materials or components supplied by the client | Supplied material is damaged, unsuitable or wrongly dimensioned |
| Work by other contractors | Screed too damp, substrate not load-bearing, previous trade not finished or faulty |
Under § 4 para. 2 no. 1 VOB/B, you carry out the work on your own responsibility and must observe the recognised rules of technology and statutory and official requirements. A specialist firm that can see that a plan breaches them must report it.
When the notice must be given
“Without delay – if possible before work starts.” That means: check the plan, material and substrate before starting, not only when things go wrong. Typical points in time:
- when clarifying the order and reviewing the plans,
- on delivery and goods-received inspection,
- when taking over the earlier work (handover of the substrate).
Anyone who only has concerns after work has started should still report them immediately, but liability for problems that were already apparent is harder to avert.
What the notice should contain
VOB/B requires written form, but no fixed wording. What is effective is what is specific and comprehensible:
- Addressee, date, construction project, contract.
- The point the concerns relate to (plan, item, material, earlier work).
- What exactly you consider faulty or unsuitable and why (standard, manufacturer’s specification, measured value, photo).
- Possible consequences if it is built that way (defect, damage, risk of accident).
- Your proposal for a remedy or the request for a decision by the client.
- Deadline for a reply.
- A statement that if the work is carried out as instructed you accept no liability for resulting defects.
- Evidence as an annex.
General sentences such as “we have concerns about the design” are not enough in a dispute. The more precisely you name the point and the consequence, the better you are protected.
And if the client insists on the instruction?
§ 4 para. 1 no. 4 VOB/B covers the case of instructions from the client that the contractor considers unjustified or inappropriate: it must raise its concerns, but must carry out the instructions on request, unless statutory or official requirements prevent it. If this causes an unjustified additional burden, the client bears the additional costs.
That means:
- If the client insists and you are sure it cannot be done that way: where there is a danger to life and limb or a breach of statutory or official requirements, you may and should refuse to carry it out.
- Otherwise you carry it out, document the instruction and your concerns and bill the additional costs.
How to enforce additional costs is explained in Nachtrag in a construction contract.
How to deliver the notice
- In writing and with proof of receipt. The client (not just the architect or site manager) should receive the letter.
- A copy to the designer if the contract provides for it or if the concerns relate to the designer’s work.
- Filing in the project folder with proof of delivery, photos and measurement records.
Typical mistakes
- Only said orally (“I told the foreman”).
- Too late: only after completion.
- Too general: without the point, the reason and the consequence.
- Sent to the wrong person.
- Wording without a decision: you do not ask how to proceed.
- Forgetting the statement that, if the client insists on the instruction, you only carry it out and are not liable.
Frequently asked questions
Do I have to report every little thing?
You must report what a specialist contractor in your position recognises or ought to recognise on a reasonable check and what can endanger the result. In case of doubt, better to report.
Is an e-mail enough?
VOB/B requires written form. Whether an e-mail is enough depends on the contract and, in a dispute, on the court. A letter with proof of receipt is safer. An e-mail is better than nothing.
Who is the right addressee?
The client. A copy goes to the designer or the site management if they prepare the decision.
Does the notice protect me from all liability?
No. It protects you from liability for defects that go back to the causes named. Your own execution errors remain your responsibility.
What if the client does not reply?
Set a deadline and document it. Then carry out only what you can answer for given your expertise. If there is danger or a breach of regulations, refuse to carry it out.
Sources and status
- § 4 para. 1 no. 4, paras. 2 and 3 VOB/B – execution (2016 version, checked against the statutory text in the BauWalker corpus)
- § 13 para. 3 VOB/B – defect claims
- Stand: 19.10.2026. How far a specialist contractor’s duty to check and warn extends in an individual case depends on case law and circumstances and was not evaluated here.
- Quotations of statutory text are given in translation; the German wording is authoritative.
How it works in BauWalker
BauWalker prepares letters such as the Bedenkenanmeldung as drafts and shows the source in § 4 and § 13 VOB/B. You check the text and decide what is sent.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
Notice of hindrance (Behinderungsanzeige) under § 6 VOB/B: deadline, content, consequences
When you must give notice of a hindrance, what the notice must contain and which claims to an extension of time and to compensation depend on it.
Warranty in construction (Gewährleistung): 4 or 5 years? VOB/B and BGB compared
How long defect claims for construction work take to become time-barred, when the period starts, what a notice of defects (Mängelrüge) achieves and which rights the client has.
Create documents – invoice, quote, change order
Invoice, quote, change order, letter and acceptance report: you describe the task in your language, BauWalker prepares the document in German.