How do you document additional construction services?
Additional services get paid if you can prove what was not in the contract, who gave the instruction and what was actually carried out.
What to record immediately
Document on the day of the work, not only when there is a dispute.
- Date and area of the work
- Instruction from the client: letter, minutes, entry in the Bautagesbericht
- Photos before and after
- hours spent, material and equipment
- Reference to the contract clause that does not cover these services
Afterwards – the Nachtrag
On the basis of this documentation, the justification and calculation are prepared. The earlier the agreement, the lower the risk of rejection.
Author, sources and status
Author: Boris Pushkarev · Last updated:
For concrete disputes, running deadlines or larger amounts, consult a lawyer (Rechtsanwalt). This article is general information and does not replace legal or tax advice for your case.
Updates
If laws, standards or case law change, the article is adjusted. The date above shows the latest change.
How it works in BauWalker
BauWalker brings together the documents of the construction project and creates the justification of the additional services.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
How does a Nachtrag work in a construction contract?
When a Nachtrag arises, what belongs in the justification and how to avoid disputes.
Projects and documents
Documents organised by project: contracts, quotes, invoices and minutes in one working context, with clear separation of data.
What must a Bautagesbericht contain?
What to record in the Bautagesbericht (daily site report) so that it helps in disputes and with Nachträge.