How does a Nachtrag work in a construction contract?
A Nachtrag is a change or addition to the contract: services that were not part of the original scope, or changed conditions of their execution.
Process
First the original contract scope is recorded, then what changed and on whose instruction, after which the justification and calculation are prepared.
- original scope of services under the contract
- description of the change and its reason
- instruction from the client or circumstance that triggered the change
- calculation of costs and deadlines
- written agreement before work begins, where possible
The biggest risk
The services have been carried out, and the justification is prepared only later and without documents. Then a dispute is almost inevitable.
Author, sources and status
Author: Ekaterina Dubnova · Last updated:
For concrete disputes, running deadlines or larger amounts, consult a lawyer (Rechtsanwalt). This article is general information and does not replace legal or tax advice for your case.
Updates
If laws, standards or case law change, the article is adjusted. The date above shows the latest change.
How it works in BauWalker
BauWalker reconciles the contract with the change and creates a draft of the Nachtrag justification, citing the contract points.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
Create documents
Invoice, quote, change order, letter and acceptance report: you describe the task in your language, BauWalker prepares the document in German.
How do you document additional construction services?
How to record additional services so that they get paid.
Reviewing a construction contract: what matters for acceptance, warranty and retention
Three points in a construction contract you should always check: acceptance, warranty and retention – with references from VOB/B and BGB.