Aufmaß under VOB/C: deduction and over-measuring by trade
How much wall area is billed depends not only on the plan but on the trade: each ATV itself regulates which openings are deducted and which are over-measured. Here you will find where the rule is and how to apply it cleanly.
Last updated 13.11.2026 · 4 min read · Provisions checked against the statute and VOB text
Key points at a glance
- The Aufmaß follows the billing provisions of the Technical Contract Conditions (§ 14 para. 2 VOB/B). These are the ATV of VOB/C, in each case section 5 "Abrechnung".
- The general rules are in ATV DIN 18299. The trade ATV (e.g. painting, tiling, plastering, drywall) supplement or change them.
- Over-measuring means: an opening or recess up to a limit is not deducted. The limit is set by the respective ATV and is different for each trade.
- The figure from the plan is not enough. What counts is what the ATV says for your trade and what has been agreed differently in the contract.
- Determinations should be made jointly if possible with the client (§ 14 para. 2 VOB/B).
Where the rule is found
A billing under VOB/B must be verifiable. The quantity calculations, drawings and other supporting documents must be attached to the invoice (§ 14 para. 1 VOB/B). Which quantities apply is determined by the billing provisions in the Technical Contract Conditions and the other contract documents; they must be observed (§ 14 para. 2 VOB/B).
For construction work under VOB/C there are two levels:
- ATV DIN 18299 (General rules for construction work of any kind): under no. 5 the work is determined from drawings, as long as the work carried out corresponds to these drawings. If there are no drawings, the work is usually measured jointly.
- The ATV of the trade (DIN 18300 series): section 5 names the billing unit (m², m, piece) and the rules for deduction and over-measuring.
Over-measuring and deducting
With wall, ceiling and floor areas, most points of dispute arise at openings and recesses: doors, windows, shafts, columns, built-in elements. The ATV sets for its trade whether and from what size such areas are deducted. Smaller openings are over-measured, so the area is billed as if they did not exist. Larger ones are deducted.
The same door can therefore be treated differently by the painter than by the tiler. Anyone who takes quantities from a plan should check before invoicing which rule belongs to which trade.
Where to look for each trade
| Trade | ATV | Where to look |
|---|---|---|
| Tiling and slab work | DIN 18352 | Section 5 "Abrechnung", rules for floor and wall coverings |
| Plastering and stucco work | DIN 18350 | Section 5 "Abrechnung" |
| Screed work | DIN 18353 | Section 5 "Abrechnung" |
| Floor covering work | DIN 18365 | Section 5 "Abrechnung" |
| Drywall work | DIN 18340 | Section 5 "Abrechnung" |
We deliberately do not state threshold values here. The DIN standard texts are not in the BauWalker corpus and cannot be checked there against the wording. Figures from forums or summaries sometimes differ from each other and apply to a particular edition. Use the values from VOB/C in the edition agreed in your contract (currently usually 2023), and enter the source reference in the invoice.
How to proceed
- Clarify the edition: Which VOB/C edition applies according to the contract? Does VOB apply at all, or does the contract deviate?
- Open the ATV for each trade: read section 5, note the deduction and over-measuring limit.
- Record openings: width and height of every door, every window and every recess. Dimensions from the plan are plan dimensions; check them on site when centimetres matter.
- Apply the rule: below the limit over-measure, above it deduct. Make every decision visible in the quantity calculation.
- Determine jointly: what will be covered later or is hard to determine should be measured in good time with the client (§ 14 para. 2 VOB/B).
- Attach supporting documents: quantity calculation and drawing belong to the invoice (§ 14 para. 1 VOB/B).
Calculation and billing are not the same
For an Angebot, many calculate honestly and simply: every known opening is deducted. For billing under VOB, the ATV applies. If your invoice deviates from the rule that a client familiar with VOB recalculates, there will be arguments on site. BauWalker therefore separates the two cases: for the calculation it deducts detected openings. Billing with over-measuring limits per trade is in preparation; the limit values are not yet confirmed from the original ATV text and will only be activated after that.
Frequently asked questions
Do I always have to deduct doors and windows?
No. Whether an opening is deducted or over-measured is regulated by the ATV of your trade in section 5. If the parties have agreed something different in the contract, that takes precedence.
Does DIN 18299 apply to all trades?
It contains the general rules for construction work of any kind. The ATV of the individual trade supplements or changes it; for your trade the combination of both counts.
Does VOB/C also apply without a VOB contract?
Only if it has been agreed. Without a VOB agreement, the billing rules of the ATV do not apply automatically; then the contract decides, in case of doubt the customary practice.
Is the dimension from the plan enough?
For billing, the work is determined from drawings, as long as the work carried out corresponds to them (ATV DIN 18299 no. 5). If the execution deviates, it must be measured on site.
How reliable are the figures BauWalker reads from the plan?
The result is a proposal. Openings are carried with an assumed height and must be checked; for vector PDFs they are not yet detected, and the wall areas are then gross.
Sources and status
- § 14 paras. 1 and 2 VOB/B – Abrechnung (2016 version, checked against the norm text in the BauWalker corpus)
- ATV DIN 18299 no. 5, determination of the work from drawings (according to VHB Bund 2017, no. 12.3.1, reading version 2023; the DIN text itself is not in the corpus)
- ATV DIN 18363, 18352, 18350, 18353, 18365, 18340, in each case section 5 "Abrechnung" (not in the corpus, threshold values therefore not stated; please take them from VOB/C in the agreed edition)
- As of: 13.11.2026. General information, not legal advice. In a dispute over quantities, you should have the contract and the ATV edition checked.
How it works in BauWalker
BauWalker reads rooms and areas from the plan, lists detected openings as separate lines and marks what you need to check. You apply the billing rule of your trade on the basis of the ATV.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
Aufmaß from the Plan: Rooms and Areas
Determine rooms, wall and floor areas from the floor plan – and calculate living area under the WoFlV. This is how Aufmaß with AI works.
Aufmaßblatt: template and mandatory details for the Aufmaß
What belongs in an Aufmaßblatt, how a joint Aufmaß proceeds and a template to copy with columns for room, dimensions, deductions and area.
Schlussrechnung (final invoice) under VOB/B: deadline, verifiability, payment
By when the final invoice must go out, what verifiable means, when the money falls due and how the reservation on final payment works.