Aufmaßblatt: template and mandatory details for the Aufmaß
An Aufmaßblatt records what was performed, in dimensions that anyone can recalculate later. Here you will find the mandatory details, the procedure and a template to copy.
Last updated 13.11.2026 · 4 min read · Provisions checked against the statute and VOB text
Key points at a glance
- An Aufmaßblatt proves the type and extent of the work with dimensions, calculation method and result. It belongs to the invoice as a quantity calculation (§ 14 para. 1 VOB/B).
- Determinations should be made jointly if possible with the client. What will be covered later must be measured beforehand (§ 14 para. 2 VOB/B).
- Mandatory: construction project, date, participants, item, dimensions, deductions, result, signatures.
- Which deductions and over-measuring rules apply depends on the ATV of your trade, not on the form.
What belongs in an Aufmaßblatt
| Detail | Why |
|---|---|
| Date and participants of both sides | Proof of who made the determination |
| Item per Angebot or LV (number and short text) | Verifiability of the billing |
| Component or room, floor | Traceability on site |
| Dimensions (length, width, height) in metres | Basis of the calculation |
| Deductions (openings, recesses) with dimensions | Proof of the quantity determination |
| Calculation method and result with unit | Recalculation without queries |
| Signature of both sides or note "einseitig" | Binding effect |
Procedure of a joint Aufmaß
- Arrange an appointment and request it in good time if work would otherwise be covered (§ 14 para. 2 sentence 3 VOB/B).
- Bring documents: plan, bill of quantities (Leistungsverzeichnis), contract, tape measure or laser.
- For each item take dimensions and enter them in the sheet.
- Apply deductions according to the ATV of the trade and note them in the sheet (see Aufmaß under VOB/C).
- Have it countersigned and keep a copy each.
- Submit with the invoice, as a quantity calculation.
For federal construction projects, the Vergabe- und Vertragshandbuch (VHB) applies. Under it, jointly determined quantities are binding for both contracting parties; the binding effect does not, however, concern the question of how they are remunerated (VHB 2017, no. 12.3.2). For private orders this applies only if so agreed.
Template to copy
AUFMASSBLATT
Bauvorhaben: [Bezeichnung, Adresse]
Auftraggeber: [Name]
Auftragnehmer: [Firma]
Vertrag / Auftrag Nr.: [Nummer] vom [TT.MM.JJJJ]
Datum des Aufmaßes: [TT.MM.JJJJ]
Teilnehmer Auftraggeber: [Name] Teilnehmer Auftragnehmer: [Name]
Gewerk / ATV: [z. B. Malerarbeiten, DIN 18363]
Pos. | Kurztext | Raum / Bauteil | Anzahl | Länge (m) | Breite (m) | Höhe (m) | Abzug (m²) | Menge | Einheit
[1.1] | [Wandfläche streichen] | [Zimmer 1] | [1] | [ ] | [ ] | [ ] | [ ] | [ ] | [m²]
[1.2] | [Decke streichen] | [Zimmer 1] | [1] | [ ] | [ ] | [ ] | [ ] | [ ] | [m²]
[1.3] | [Sockelleiste] | [Zimmer 1] | [1] | [ ] | | | | [ ] | [m]
Abzüge im Einzelnen (Öffnungen, Aussparungen mit Maßen):
[Tür 0,885 m × 2,01 m = 1,78 m²]
[Fenster 1,01 m × 1,26 m = 1,27 m²]
Angewandte Abrechnungsregel: [ATV, Abschnitt 5, Grenze für Übermessung]
Bemerkungen: [ ]
Ort, Datum: [ ]
Unterschrift Auftraggeber: ______________________
Unterschrift Auftragnehmer: ______________________
With a plan: determine quantities faster
If a floor plan is available, you do not have to measure rooms and areas by hand from the plan. Aufmaß KI from BauWalker reads rooms as well as wall and floor areas from PDF, DWG, DXF or photo, calculates the living area under WoFlV and lists detected doors and windows as separate lines. The result is a proposal: you check it before you transfer it into an Angebot or billing. More at Aufmaß KI.
Frequently asked questions
Does an Aufmaß have to be done jointly?
Under § 14 para. 2 VOB/B, the necessary determinations should be made jointly if possible, in line with the progress of the work. That is not compulsory, but a joint Aufmaß avoids later disputes.
What if the client does not sign?
Document the appointment and the invitation, take the Aufmaß anyway and note "einseitig". Bill verifiably on the basis of dimensions and drawings.
In which units is it measured?
The unit per item is stated in the contract and in the ATV of the trade (e.g. m², m, piece). Enter dimensions in metres, results with the unit of the item.
Is a photo enough as an Aufmaß?
A photo documents the condition but does not replace the dimension sheet. For billing you need dimensions and calculation method.
Is the template available as a file?
Here it is given as text to copy into Word or Excel. Aufmaße from BauWalker can be exported as Excel or CSV.
Sources and status
- § 14 paras. 1 and 2 VOB/B – Abrechnung (2016 version, checked against the norm text in the BauWalker corpus)
- VHB Bund 2017 (reading version 2023), no. 12.3 – Leistungsfeststellung und Leistungserfassung (administrative regulation for federal construction projects, not a law)
- As of: 13.11.2026. The form is a sample; adapt it to your contract and your trade.
How it works in BauWalker
If a plan is available, BauWalker reads rooms and areas from it and provides them as a list to check, with export as Excel or CSV. It does not replace the Aufmaßblatt on site when measuring jointly.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
Aufmaß from the Plan: Rooms and Areas
Determine rooms, wall and floor areas from the floor plan – and calculate living area under the WoFlV. This is how Aufmaß with AI works.
Aufmaß under VOB/C: deduction and over-measuring by trade
How openings and recesses are treated in the Aufmaß, where the rules are found (ATV, section 5 Abrechnung) and what to watch for in each trade.