Knowledge · Templates & checklists
Sample: notice of hindrance (Behinderungsanzeige) under § 6 VOB/B
This template contains everything a notice of hindrance under § 6 para. 1 VOB/B needs. Adapt the placeholders in square brackets to your case and send the letter in a provable way.
Last updated 20.10.2026 · 4 min read · Sample, to be adapted to the individual case

Key points at a glance
- Give notice of the hindrance without delay and in writing (§ 6 para. 1 VOB/B).
- State the cause, period, affected work and expected consequences.
- Request a remedy with a deadline and reserve your claims (§ 6 paras. 2, 4, 6 VOB/B, § 642 BGB).
- Send it provably (registered letter by hand delivery, messenger, confirmed e-mail) and file the proof and annexes.
How to use the sample
- Copy the text below.
- Replace all details in square brackets with your data. Delete what does not fit.
- Attach evidence: photos, daily report (Bautagesbericht), e-mail history, plans.
- Check whether your contract prescribes a form or an addressee.
- Send the letter with proof of receipt.
The explanation is at Behinderungsanzeige under § 6 VOB/B.
Sample text
The sample letter is in German on purpose, because it is sent to a German counterpart; fill it in as it stands and do not translate it.
[Absender: Firma, Anschrift, Ansprechpartner, Telefon, E-Mail]
[Empfänger: Auftraggeber, Anschrift]
[ggf. Kopie an: Bauleitung / Architekt]
[Ort], den [TT.MM.JJJJ]
Per [Einwurf-Einschreiben / Bote / E-Mail mit Empfangsbestätigung]
Bauvorhaben: [Bezeichnung, Adresse]
Vertrag vom [TT.MM.JJJJ], Auftragsnummer [Nummer]
Gewerk: [z. B. Trockenbau, Elektro]
Behinderungsanzeige nach § 6 Abs. 1 VOB/B
Sehr geehrte Damen und Herren,
hiermit zeigen wir Ihnen gemäß § 6 Abs. 1 VOB/B an, dass wir in der ordnungsgemäßen Ausführung unserer Leistung behindert sind.
1. Art der Behinderung
[Beschreiben Sie konkret, was Sie hindert, z. B.: Der Estrich im [Bereich] ist nicht fertiggestellt, sodass wir unsere Arbeiten nicht beginnen können.]
2. Zeitraum
Die Behinderung besteht seit dem [TT.MM.JJJJ]. Sie dauert voraussichtlich bis [TT.MM.JJJJ / unbekannt] an.
3. Ursache
[Beschreiben Sie die Ursache und den Bereich, aus dem sie stammt, z. B.: Die Freigabe der Ausführungsplanung für [Bereich] liegt bis heute nicht vor.] Diese Ursache liegt nach unserer Einschätzung in Ihrem Risikobereich / im Risikobereich von [Name].
4. Betroffene Leistungen und Termine
[Nennen Sie die betroffenen Leistungspositionen und Termine, z. B.: Betroffen sind die Positionen [Nr.] bis [Nr.]. Der vertraglich vereinbarte Fertigstellungstermin [TT.MM.JJJJ] ist dadurch gefährdet.]
5. Auswirkungen
Die Behinderung führt voraussichtlich zu einer Verlängerung der Ausführungsfrist nach § 6 Abs. 2 und 4 VOB/B um [Anzahl] Werktage zuzüglich eines Zuschlags für die Wiederaufnahme der Arbeiten und eine etwaige Verschiebung in eine ungünstigere Jahreszeit. Mit zusätzlichen Kosten ist [zu rechnen / nicht zu rechnen] (Stillstand, Vorhaltung, Wiederanlauf). Wir beziffern diese, sobald die Dauer feststeht.
6. Aufforderung zur Abhilfe
Wir fordern Sie auf, die Behinderung bis zum [TT.MM.JJJJ] zu beseitigen bzw. uns mitzuteilen, wie und wann Sie Abhilfe schaffen. Wir halten uns bereit, die Arbeiten unverzüglich aufzunehmen, sobald die hindernden Umstände entfallen sind (§ 6 Abs. 3 VOB/B).
7. Vorbehalt
Wir behalten uns ausdrücklich vor, Fristverlängerung nach § 6 Abs. 2 VOB/B, Ersatz unseres nachweislich entstandenen Schadens nach § 6 Abs. 6 VOB/B sowie angemessene Entschädigung nach § 642 BGB geltend zu machen. Weitere Rechte bleiben vorbehalten.
Anlagen:
[1. Foto-Dokumentation vom [Datum]]
[2. Bautagesbericht vom [Datum]]
[3. Schriftverkehr vom [Datum]]
Mit freundlichen Grüßen
[Unterschrift, Name, Funktion]
Filling-in help
| Place | What to watch for |
|---|---|
| Subject line | Name § 6 para. 1 VOB/B expressly. This makes it easier to assign. |
| Items 1 and 3 | Specific rather than general. Date, place, trade. |
| Item 4 | Name items and dates. Avoid blanket assertions. |
| Item 5 | Estimate only what you can stand behind. Reserve the exact calculation. |
| Item 6 | Set a reasonable deadline. |
| Item 7 | The reservation protects your rights. Delete what does not fit your situation. |
| Annexes | Evidence increases probative value. Photos with a date. |
Do not use the sample unchanged for every new hindrance. For a new cause, draw up a new notice.
After sending
- File the proof of receipt (receipt for posting, acknowledgement of receipt).
- Keep a daily report (Bautagesbericht): hindrance, effects, measures.
- Note the deadline in the calendar, follow up when the deadline expires.
- When the hindrance ends: resume work without delay and notify the client (§ 6 para. 3 VOB/B).
Frequently asked questions
May I use the sample unchanged?
No. It is a template. Make the cause, period and affected work specific, otherwise the notice is open to attack.
Is notice by e-mail enough?
Whether an e-mail is enough depends on the contract. Choose a method where you can prove receipt, for example a registered letter by hand delivery or a confirmed e-mail.
Do I have to quantify the additional costs immediately?
No. Reserve the calculation and submit it later, once the duration and extent are known.
Does the sample apply to BGB contracts?
The duty to give notice in this form is in VOB/B. In a BGB contract, written notice still makes sense in order to prove claims (for example under § 642 BGB).
Sources and status
- § 6 paras. 1 to 7 VOB/B (2016 version, checked against the statutory text in the BauWalker corpus); § 642 BGB
- Stand: 19.10.2026. This sample is a general template and does not replace legal advice. Check your contract for deviating requirements on form and deadlines.
- Quotations of statutory text are given in translation; the German wording is authoritative.
How it works in BauWalker
BauWalker prepares letters such as the Behinderungsanzeige as drafts when you describe the situation in your own words. You check the text and deadlines and decide what is sent.
This material is for information and is not legal or tax advice. The specific consequences depend on your contract and the circumstances on the construction site.
Keep reading
Notice of hindrance (Behinderungsanzeige) under § 6 VOB/B: deadline, content, consequences
When you must give notice of a hindrance, what the notice must contain and which claims to an extension of time and to compensation depend on it.
What must a Bautagesbericht contain?
What to record in the Bautagesbericht (daily site report) so that it helps in disputes and with Nachträge.
Create documents – invoice, quote, change order
Invoice, quote, change order, letter and acceptance report: you describe the task in your language, BauWalker prepares the document in German.